Wind Farm
Banie

Evergy was mandated to provide Technical Due Diligence and Owner’s Engineering services for the Banie Wind Farm, a large-scale development implemented over six partially overlapping construction phases between 2015 and 2024.

The Banie project includes 96 turbines grouped into eight sub-projects, located south of Stettin, near the Germany border. At the time of engagement, the sub-projects were in development. The wind farm is connected to the Polish transmission grid via a 400 kV transformer station, through a project-owned internal grid infrastructure that includes three additional transformer stations.

The services of Evergy comprised in particular:

  • Multiple bankable energy yield assessments for different phases
  • Support in negotiating turbine supply agreements
  • Layout optimization
  • Grid curtailment impact analysis and optimization
  • Detailed electrical loss and load flow simulations using DIgSILENT PowerFactory
  • Evaluation of hybridization potential for selected project segments

Country

Poland

Year of Mandate

2015

Key Technical Data

  • 96 wind turbines, 192 MW total installed capacity

Services

Energy Forecasts

Optimisation of Existing Projects

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Banie
Rihab Benlyas tea lover, working @evergy since 2021
Chaque projet vient avec son lot de défis. J'ai travaillé sur l'analyse des données opérationnelles de plusieurs centaines de centrales photovoltaïques réparties dans 9 pays. Cette tâche m'a donné un aperçu de la technologie, des contraintes géographiques et de la qualité de la maintenance - tout cela sans mettre un pied à l'intérieur des centrales.
Every project comes with its challenges. I have worked on the Operational Data Analysis of several hundred PV plants spread over 9 countries. This task gave me insight on the technology, geography constraints and quality of maintenance - all without taking a single “physical” step inside the plants.
meet Rihab