Evergy was commissioned to perform a Confirmatory Technical Due Diligence of five operational hydroelectric power plant schemes across Norway.

The run-of-river plants are geographically distributed between Oslo in the south and Tromsø in the north. Commissioned between November 2011 and December 2015, the plants range in nominal capacity from 1.3 MW to 5.5 MW each. All installations are connected at the medium-voltage level to the respective local distribution networks.

The services of Evergy comprised in particular:

  • Verification of the specific catchment area and hydrological flow assessments
  • Energy yield assessment based on operational data
  • Identification of technical issues affecting operational performance
  • Structural integrity verification of the power plant infrastructure
  • On-site inspection and evaluation of current technical condition
  • Preparation of a refurbishment strategy with estimated cost implications

Country

Norway

Year of Mandate

2022

Key Technical Data

  • Portfolio of 5 run-of-river hydroelectric plants with approx. 16 MW total installed capacity

Services

Energy Forecasts

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Tikraft
Dirk Zeyringer Walker, working @evergy since 2007
Evergy steht für vielfältige, herausfordernde Projekte mit sich schnell weiterentwickelnden Technologien. Ein für mich besonderes Projekt haben wir aktuell in Bangladesch. Dabei beraten wir in Kooperation mit einem Partnerunternehmen eine staatliche Finanzinstitution, die Kredite an Unternehmen, Investoren und NGOs zur Finanzierung von Erneuerbaren Energien vergibt.
Evergy stands for diverse, challenging projects with rapidly evolving technologies. One of my favourite projects is currently in Bangladesh. In cooperation with our partner company, we are advising a state financial institution that provides loans to companies, investors and NGOs for financing renewable energies.
meet Dirk