PV Power Plant Windhoek, Namibia

Execution Planning for a 3.8 MWp PV Power Plant

The objectives of the assignment were:

  • Preparation of execution planning for construction

The scope of work covered the following aspects:

  • Electrical design
  • Civil and infrastructure design
  • Bill of materials

Execution Planning for a 3.8 MWp PV Power Plant

Country

Namibia

Year of Mandate

2016

Year of Commisioning

2017

Key Technical Data

  • Total capacity: 3.8 MWp
  • PV technology: poly crystalline
  • Inverter manufacturer: SMA Solar Technology
  • Grid connection: 11 kV substation