Evergy was engaged to provide technical advisory for the transaction of the Eifel Wind Farm, which formed part of a larger asset portfolio. Since then, Evergy has continued to deliver ongoing technical consultancy services for the project.

The Eifel Wind Farm was constructed in three phases between 2005 and 2007, incorporating wind turbines from Nordex and Enercon. The turbines are connected to a private transformer substation operating at 110 kV.

The services of Evergy comprised in particular:

  • Technical Due Diligence for the operational asset at the time of transaction
  • Ongoing energy yield assessments based on production data
  • Performance evaluation and technical availability analysis
  • Assessment of turbine retrofit options and technical enhancements
  • Ongoing consultancy on operational and regulatory aspects
  • Regular reporting of key technical and financial indicators
  • Technical advisory on extension and renegotiation of operational project contracts

Country

Germany

Year of Mandate

2011

Key Technical Data

  • 23 wind turbines (Nordex S70/S77 and Enercon E-70)

Services

Energy Forecasts

Optimisation of Existing Projects

Technical Due Diligence

Evergy Engineering GmbH » Eifel
Pierre Dutilleux sailor, working @evergy since 2010
Le déroulement d’un projet est captivant : il arrive que, dès les premières investigations, on flaire certains problèmes qui par la suite se révèleront critiques et pour lesquels, en définitive, une solution devra être trouvée.
It's exciting to follow the development of a project: The initial project analysis often gives you a sense of potential problems that then really do become acute and need to be solved.
meet Pierre