Evergy was mandated to perform Technical Due Diligence for the acquisition of a diversified portfolio comprising eight solar PV plants with a cumulative capacity of 256 MWp.

The PV assets are situated in the Emilia-Romagna region in northern Italy. The portfolio includes two projects planned with single-axis tracking systems, five with fixed-tilt structures and east-west orientation, and one floating PV installation. At the time of engagement, several plants had received permitting approval, while others were still progressing through the permitting process.

The services of Evergy comprised in particular:

  • Assessment of development status and probability of achieving “ready-to-build” status
  • Evaluation of permitting documentation and regulatory alignment
  • Recommendations for technical design optimisation
  • Feasibility analysis of design modifications with respect to permitting approval
  • Review and plausibility assessment of existing energy yield evaluations

Country

Italy

Year of Mandate

2024

Key Technical Data

  • 8 PV plants totalling 256 MWp, comprising fixed-tilt, single-axis tracker and floating PV systems

Services

Energy Forecasts

Optimisation of Existing Projects

Technical Due Diligence

Evergy Engineering GmbH » Hive
Daniel Schönberger open-minded bavarian, working @evergy since 2020
Beeindruckend war das Queenfisher-Projekt: ein Portfolio von über 20 Projekten. Und das gleich als Einstieg mit Besuch in einem anderen Land und umfangreicher Mitarbeit.
The Queenfisher project was impressive: a portfolio of over 20 projects. Including a visit to another country and extensive work right from the start.
meet Daniel
Explore more Portfolio projects