Hybrid Project
Scruf Dyke

Evergy provided comprehensive lender’s technical due diligence services for the Scurf Dyke Hybrid Power Plant in the UK. The scope included a detailed review of construction timelines, technology selection, permitting, grid connection arrangements, financial model assumptions, ESG compliance, and all key project contracts.

The Scurf Dyke project comprises an 80 MWp solar PV plant integrated with an 8 MW / 16 MWh battery energy storage system (BESS)—the largest of its kind in the UK at the time of engagement. The project was in the development stage and required close coordination among the developer, equity investor, and debt provider.

The services of Evergy comprised in particular:

  • Lender's Technical Due Diligence
  • Construction monitoring with regular site inspections and detailed risk analysis
  • Technical inspections at key milestones (Provisional and Final Acceptance - PAC and FAC)

Country

United Kingdom

Year of Mandate

2024

Key Technical Data

  • 80 MWp PV Plant, 8 MW / 16 MWh BESS

Services

Energy Forecasts

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Scurf Dyke
Daniel Schönberger open-minded bavarian, working @evergy since 2020
Ich arbeite in unterschiedlichen Bereichen, z. B. testgetriebene Entwicklung, laufende Betreuung und Baufortschrittskontrolle. Auch die Dachanlagenprojekte sind immer anders.
I work in different areas, e.g. test-driven development, support and construction progress control. Especially the roof system projects are always different.
meet Daniel