Evergy was appointed to carry out Technical Due Diligence in support of the acquisition process of two operational hydroelectric power plants in Scotland. Both plants have been in operation since 2015.

The Derrydarroch and Upper Falloch facilities are run-of-river systems located within the same hydrological catchment area, with gross heads ranging from 120 m to 213 m. The installed capacities are 0.9 MW and 2.0 MW respectively. Both plants are connected to the local medium-voltage distribution grid.

The services of Evergy comprised in particular:

  • Verification of the specific catchment area and flow rate assessment
  • Energy yield assessment using operational data
  • Technical design review
  • Site inspection and assessment of the current technical condition
  • Development of a refurbishment strategy with associated cost estimation
  • Review of existing Operation & Maintenance (O&M) contracts

Country

United Kingdom

Year of Mandate

2021

Key Technical Data

  • 2 run-of-river hydroelectric power plants, approx. 3 MW combined capacity

Services

Energy Forecasts

Technical Due Diligence

Technical Inspection

Evergy Engineering GmbH » Derrydarroch and Upper Falloch
Rihab Benlyas tea lover, working @evergy since 2021
Après avoir travaillé dans un laboratoire de recherche pendant quelques années, j'ai voulu m'impliquer dans le secteur des énergies renouvelables à une échelle plus concrète. Aujourd'hui, je suis fière d'aider au développement, à la construction et à l'exploitation de projets d'énergies renouvelables, en tant que consultante.
After working in a laboratory for some years, I wanted to be involved in the field of renewable energies on a more tangible scale. Now, I am proud to assist with the development, construction, and operation of renewable energy projects, from a technical consultant’s point of view.
meet Rihab
Explore more Hydro projects