Evergy was engaged to provide technical advisory for the transaction of the Eifel Wind Farm, which formed part of a larger asset portfolio. Since then, Evergy has continued to deliver ongoing technical consultancy services for the project.

The Eifel Wind Farm was constructed in three phases between 2005 and 2007, incorporating wind turbines from Nordex and Enercon. The turbines are connected to a private transformer substation operating at 110 kV.

The services of Evergy comprised in particular:

  • Technical Due Diligence for the operational asset at the time of transaction
  • Ongoing energy yield assessments based on production data
  • Performance evaluation and technical availability analysis
  • Assessment of turbine retrofit options and technical enhancements
  • Ongoing consultancy on operational and regulatory aspects
  • Regular reporting of key technical and financial indicators
  • Technical advisory on extension and renegotiation of operational project contracts

Country

Germany

Year of Mandate

2011

Key Technical Data

  • 23 wind turbines (Nordex S70/S77 and Enercon E-70)

Services

Energy Forecasts

Optimisation of Existing Projects

Technical Due Diligence

Evergy Engineering GmbH » Eifel
Marc Böhnke sailor, working @evergy since 2007
Die Erwartungen unserer KundInnen sind hoch, die müssen und wollen wir auch erfüllen. Das geht nur durch persönliches Engagement und Fokus auf die Kundenbedürfnisse.
Our clients’ expectations are high and we have to, and want to, fulfill them. This can only be achieved through personal commitment and a focus on our clients’ needs.
meet Marc